To date, DCSi has successfully completed approximately 500 projects. Scopes of work span design/constructibility reviews, inspection services, commissioning, retro-commissioning and recommissioning, forensic investigation, progress payment inspections, commercial building inspections, condition assessments, and power-quality studies.
We hope to illustrate the breadth of commissioning services that we offer as well as to connect you with any of our clients for a referral about our work. If you would like to talk with any of the clients listed below, contact us at (702) 942-1616 or email us at: info@LV-DCSi.com.
|
OTHER LEED PROJECTS CURRENTLY IN PROGRESS OR CONTRACTED
 |



 |
| PROJECT NAME: DESERT LIVING CENTER |
| PROJECT DESCRIPTION: |
The Desert Living Center is the “green” jewel in the crown of the Las Vegas Springs Preserve. The Desert Living Center buildings are the first platinum LEED® (Leadership in Energy and Environmental Design) buildings in the state of Nevada. These buildings embody the Preserve’s message of sustainability.
The Desert Living Center is made up of five buildings and the surrounding gardens.
Unique Aspects of this Project: |
|
Rammed-earth walls utilizing local materials |
|
Window design maximizing natural daylight use |
|
Recycled materials minimizing new resource demand |
|
Passive cooling and renewable heating of buildings |
|
Reclaimed water to reduce tap-water needs |
|
Electrical energy created by solar panels |
The following is a list of included systems: LEED Fundamental Commissioning of: |
|
Mechanical |
|
DDC Controls |
|
Electrical Distribution |
|
Lighting/Lighting Controls |
|
Fire Life-Safety Equipment and Systems |
|
DCSI Commissions First LEED® NC Platinum-Level Project in Nevada
DCSI has commissioned the first LEED NC Platinum-level project in Nevada: The Desert Living Center at the Las Vegas Springs Preserve. The designation, the highest a building can receive from the U.S. Green Building Council, requires that a majority of required building materials be recycled, re-used or recyclable, among other things.  |
 |
| PROJECT NAME: LAS VEGAS SPRINGS PRESERVE |
| PROJECT DESCRIPTION: |
The $250 million Las Vegas Springs Preserve aims to be Nevada's first LEED Platinum project. It will provide space for the Nevada State Museum, Visitor's Center and the Desert Living Center interspersed among restored wetlands. It will include more than 176,000 square feet of museums, educational galleries and interactive exhibits. It will eventually include the 79,000-square-foot Nevada State Museum that is expected to open in 2009.
Unique Aspects of this Project: |
|
It will be the first attraction in the U.S. to achieve LEED (Leadership in Energy and Environmental Design) Platinum Certification. |
|
It is the largest commercial straw-bale project in the U.S. |
|
Solar panels on site will generate enough solar energy to power approximately 70 percent of the Preserve attraction. |
|
The Preserve is home to more than 250 species of wildlife. |
|
Water on site will be filtered and reused to irrigate plants and flush toilets at the Preserve. |
| The following is a list of included systems: |
|
Mechanical |
|
DDC Controls |
|
Electrical Distribution |
|
Lighting/Lighting Controls |
|
Fire Life-Safety Equipment and Systems |
|
| PROJECT NAME: DEPARTMENT OF EMPLOYMENT TRAINING AND REHABILITATION |
| PROJECT DESCRIPTION: |
One 64,000-square-foot, two-story office building with public and private program spaces including a call center, training rooms, warehouse facilities and administrative offices.
|
| The systems consist of: |
|
Central Plant |
|
Full DDC |
|
Monitoring and Daylighting Controls |
|
HVAC Underfloor Air System |
|
Fire Alarm/Fire Detection |
|
Chilled Water/Heating Water |
|
Plumbing |
|
Data, Power and Communications Distribution |
This project is pursuing Silver Certification through the U.S. Green Building Council’s LEED Green Building Rating System. |
| Brief summary of included systems: |
|
Mechanical:
Air Handling Units and VAVs with Reheat Coils: All air moving equipment and associated controls.
Hot-Water System: Hot-water system and all associated equipment and controls.
Chilled Water System: Chilled water system and all associated equipment and controls. |
|
Life Safety:
Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers.
Duct Detector Verification: Verify smoke detectors installation and function. |
|
Electrical:
Electrical Distribution System: Commissioning includes: switchboards, motor control centers, panelboards, enclosed starters, variable frequency drives, transformers, enclosed transfer switch, packaged generator, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets).
Lighting: Verify luminaire function (and associated controls), for both interior and exterior fixtures.
Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion. |
|
| PROJECT NAME: NEVADA POWER SOUTH OPERATIONS PROJECT #1 |
| PROJECT DESCRIPTION: |
The scope consists of three buildings.
|
|
One Office Building – 35,993 square feet |
|
One Shop Building – 60,434 square feet |
|
One System Control Building – 27,000 square feet |
|
(Optional) Central Plant |
|
Full DDC |
| Brief summary of included systems: |
|
Mechanical:
Air Handling Units and VAVs with reheat coils: Air handling units, variable frequency drives for air handling units, RTUs, exhaust fans, DX split-systems.
Hot-Water System: Boilers, pumps, VFDs and associated controls
Chilled Water System: Water-cooled chillers, chilled water pumps, cooling tower pumps, cooling tower, VFDs, solids separator, and DDC controls. |
|
Life Safety:
Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers.
Duct Detector Verification: Verify smoke detectors installation and function. |
|
Electrical:
Electrical Distribution System: Commissioning includes: switchboards, motor control centers, panelboards, enclosed starters, variable frequency drives, transformers, enclosed transfer switch, packaged generator, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets).
Emergency Generator: Commissioning includes confirming settings match contract documents, witness loadbank testing and startup, verify shunt-trip and emergency load energization.
Lighting: Verify luminaire function (and associated controls), for both interior and exterior fixtures.
Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion. |
|
| PROJECT NAME: NEVADA POWER SOUTH OPERATIONS PROJECT #2 |
| PROJECT DESCRIPTION: |
| The scope consists of two buildings. |
|
One Fleet Building – 18,996 square feet |
|
One Warehouse Building – 35,883 square feet |
|
Total project square footage - 54,879 square feet |
| Brief summary of included systems: |
| |
Mechanical:
Air Handling Units and VAVs : Including air handling units, variable frequency drives for air handling units, RTUs, exhaust fans, DX split-systems.
Hot-Water System: Including boilers, pumps, electric re-heat coils in terminal boxes where heat is required, VFDs and associated controls
Chilled Water System: Including DX RTU, water-cooled chillers, chilled water pumps, cooling tower pumps, cooling tower, VFDs, solids separator, and DDC controls. |
|
Life Safety:
Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers.
Duct Detector Verification: Verify smoke detectors installation and function. |
| |
Electrical:
Electrical Distribution System: Commissioning includes, switchboards, motor control centers, panelboards, enclosed starters, variable frequency drives, transformers, enclosed transfer switch, packaged generator, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets)
Lighting: Verify luminaire function (and associated controls), for both interior and exterior fixtures.
Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion. |
|
| [ Back to top ] |
BUILDING COMMISSIONING (NEW CONSTRUCTION)
 |
 |
| PROJECT NAME:
CENTENNIAL HILLS COMMUNITY CENTER |
| PROJECT DESCRIPTION: |
A 98,000-square foot community center, located on 18 acres in Centennial Hills Park, features indoor and outdoor swimming pools, two gymnasiums, a dance room, fitness center, an active adult wing and space for a variety of multi-generational activities. |
| The following is a list of included systems: |
|
Mechanical |
|
DDC Controls |
|
Electrical Distribution |
|
Lighting/Lighting Controls |
|
Fire Life-Safety Equipment and Systems |
|
 |
| PROJECT NAME: DEL SOL HIGH SCOOL |
| PROJECT DESCRIPTION: |
One approximately 271,040-square-foot (interior) educational building complex |
|
Consisting of six buildings, three of which are two-story structures |
|
Central Plant |
|
Full Direct Digital Controls |
|
Electrical Distribution and Lighting |
|
MATV and Clock/Intercom |
|
Life-Safety |
| The following is a list of included systems: |
|
Air Handling and Ventilation Systems (multi-zones, fan coil units, heat pump, paint spray booth fan, fume hoods, MUAs, sawdust collector, relief fans and exhaust fans) |
|
Hot Water System (three boilers and water heaters) |
|
Chilled Water System (two chillers and associated pumps, two cooling towers, one heat exchanger) |
|
Hydronic Flushing Participation |
|
Power Distribution System |
|
Emergency Power System |
|
Lighting (interior/exterior) |
|
Clock/Intercom System |
|
MATV System |
|
Life-Safety Systems |
| Brief summary of included systems: |
|
Power Distribution System: Including switchboards, panelboards, motor control centers, transformers, enclosed starters, shunt-trip operation, surge protection devices, control devices, disconnect switches, GFI receptacles, fuses and overload heaters are installed in accordance with the contract documents. |
|
Thermal Imaging: Thermal imaging analysis of all feeder terminations including panels, switchboards, motor control centers, transformers, chillers and air-handlers. |
|
Grounding: Including review of electrical system grounding test reports. |
|
Emergency Power System: Including generator and automatic transfer switch |
|
General Lighting and Exterior Lighting Systems: Including interior, exterior and emergency lighting and associated controls. |
|
MATV Systems: Including labeling of outlets, antenna grounding, coordination with CCSD MATV representative. |
|
Clock/Intercom System: Including head-end equipment rack, office call-in display, clock/intercom locations, individual call-in functions, all call-function. |
|
Life-Safety Systems: Including fire alarm system, duct detectors, fire smoke dampers |
|
 |
| PROJECT NAME: CADWALLADER MIDDLE SCHOOL |
| PROJECT DESCRIPTION: |
One approximately 126,000-square-foot educational building complex |
|
Consisting of six buildings, all of which are single-story structures |
|
Central Plant |
|
Full DDC |
| The following is a list of included systems: |
|
Air Handling and Ventilation Systems (multi-zones, fan coil units, heat pump and exhaust fans) |
|
Hot Water System (boilers and water heater) |
|
Chilled Water System (chiller and associated pumps) |
|
Hydronic Flushing Participation |
|
Duct Detector Certification |
|
Fire Smoke Damper Testing |
|
Low-Voltage: |
| |
Data, CTV/MATV, Clock/Intercom, Fire Alarm System
Electrical Distribution:
Lighting, Grounding, Distribution Equipment, Generator |
|
| PROJECT NAME: VIRGIN VALLEY ELEMENTARY SCHOOL |
| PROJECT DESCRIPTION: |
One approximately 67,000-square-foot educational building complex |
|
Consisting of one contiguous building, all of which are single-story structures |
|
Central Plant |
|
Full DDC |
| Brief summary of included systems: |
|
Air Handling and Ventilation Systems: (6) triple-deck multi-zones with (76) zones, (4) fan coil units, (9) exhaust fans, (6) variable frequency drives for multi-zones, (1) VFD for cooling tower, (1) unit heater (UH-1), (2) split-systems (DX-1, 2), (1) heat pump. |
|
Hot-Water System: (1) boiler, (2) pumps and associated controls |
|
Chilled Water System: (1) water-cooled chiller, (2) chiller pumps, (2) cooling tower pumps, (1) cooling tower, (1) heat exchanger and DDC controls. |
|
Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers. |
|
Duct Detector Verification: Verify smoke detectors installation and function. |
|
Electrical Distribution System: Commissioning includes: switchboards, motor control centers, panelboards, enclosed starters, variable frequency drives, transformers, enclosed transfer switch, packaged generator, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets). |
|
Lighting: Verify luminaire function and associated controls, for both interior and exterior. |
|
Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion. |
|
Data Systems: Witness contractor ping tests of: OFE data switches, IDF locations, LAN and 555 data outlets. Verify labeling of cable and data ports. |
|
Clock/Intercom: Witness contractor operation of office call-in display, individual call-in locations, all-call function and clock locations. |
|
Stand Alone Intrusion Detection System: Witness contractor operation of intrusion detection devices and keypads, per specification 16726. |
|
MATV: Witness contractor testing to verify validity of test report results, per specification 16750, 3.4 and 3.5. |
|
CCTV Surveillance System: Witness contractor testing and recording of test results, per specification 16761, 3.2. |
|
Public Address System: Witness contractor testing and recording of test results, per specification 16770, 3.5. |
|
| PROJECT NAME: CONNERS ELEMENTARY SCHOOL |
| PROJECT DESCRIPTION: |
One approximately 67,000-square-foot educational building complex |
|
Consisting of one contiguous building, all of which are single-story structures |
|
Central Plant |
|
Full DDC |
| Brief summary of included systems: |
|
Mechanical:
Air Handling and Ventilation Systems: (6) triple-deck multi-zones with (76) zones, (4) fan coil units, (8) exhaust fans, (6) variable frequency drives for multi-zones, (1) VFD for cooling tower, (1) unit heater, (1) split-system, (2) rooftop units, (1) supply fan.
Hot-Water System: (1) boiler, (2) pumps and associated controls
Chilled Water System: (1) water-cooled chiller, (2) chiller pumps, (2) cooling tower pumps, (1) cooling tower, and DDC controls. |
|
Life Safety:
Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers.
Duct Detector Verification: Verify smoke detectors installation and function.
Fire Alarm System: Verify device installation and system function. |
|
Electrical:
Electrical Distribution System: Commissioning includes: switchboards, motor control centers, panelboards, enclosed starters, variable frequency drives, transformers, enclosed transfer switch, packaged generator, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets).
Lighting: Verify luminaire function (and associated controls), for both interior and exterior.
Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion. |
|
| PROJECT NAME: TANAKA ELEMENTARY SCHOOL |
| PROJECT DESCRIPTION: |
One approximately 67,000-square-foot educational building complex |
|
Consisting of one contiguous building, all of which are single-story structures |
|
Central Plant |
|
Full DDC |
| Brief summary of included systems: |
|
Mechanical:
Air Handling and Ventilation Systems: (6) triple-deck multi-zones with (76) zones, (4) fan coil units, (8) exhaust fans, (6) variable frequency drives for multi-zones, (1) VFD for cooling tower, (1) unit heater, (1) split-system, (2) rooftop units, (1) supply fan.
Hot-Water System: (1) boiler, (2) pumps and associated controls
Chilled Water System: (1) water-cooled chiller, (2) chiller pumps, (2) cooling tower pumps, (1) cooling tower, and DDC controls. |
|
Life Safety:
Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers.
Duct Detector Verification: Verify smoke detectors installation and function.
Fire Alarm System: Verify device installation and system function. |
|
Electrical:
Electrical Distribution System: Commissioning includes: switchboards, motor control centers, panelboards, enclosed starters, variable frequency drives, transformers, enclosed transfer switch, packaged generator, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets).
Lighting: Verify luminaire function (and associated controls), for both interior and exterior.
Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion. |
|
| [ Back to top ] |
REMODELS / RETRO-COMMISSIONING
 |
 |
| PROJECT NAME: VALLEY HIGH SCHOOL THEATER ADDITION |
| PROJECT DESCRIPTION: |
The work consists of a new Theater Building, which includes general construction and site work. The building is approximately 14,900 square feet and includes masonry, stud and stucco exterior walls, steel structural frame, built-up roof on rigid insulation on metal deck on open web steel joists with steel beams and a concrete slab-on-grade foundation. The theater has a stage that includes a fly loft with a counterweighted rigging system, stage sound and lighting systems and fixed seating.
|
| Brief summary of included systems: |
|
Ductless split-system air-conditioning unit: (4) total: (2) 1-ton and (2) 2.5-ton unit |
|
Packaged Rooftop Units: (1) 40-ton, (2) 12.5-ton, and (2) 8.5-ton gas-pack units |
|
Exhaust Fans: (4) belt-driven |
|
Controls associated with the above-mentioned equipment. |
|
Electrical Distribution System: Commissioning includes: switchboards, panelboards, enclosed starters, transformers, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets).
(Refer to Specification 16410, 3.4A. for enclosed starters.)
(Refer to Specification 16426 – DCSi will verify contractor compliance with NETA ATS in accordance with Section 1.3D.)
(Refer to Specification 16442, 3.2 and 3.3 – DCSi will verify contractor compliance.)
(Refer to Specification 16461 – DCSi will verify noise measurement, grounding and contractor compliance with Section 3.5A.)
(Refer to Specification 16151 – DCSi will verify function of wiring devices.) |
|
Lighting: Verify luminaire function measure lighting levels, (as related to Specification 16510).
(Refer to Specification 16510 – Adjustment and cleaning to be by the Division 16 Contractor.) |
|
Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion. (Refer to Specification 16050 and 16170.) |
|
| PROJECT NAME: BRIDGER MIDDLE SCHOOL PROJECT |
| PROJECT DESCRIPTION: |
One approximately 106,924-square-foot educational building complex
|
|
Consisting of twelve buildings, all of which are single-story structures |
|
Central Plant – two-pipe system |
|
Full DDC |
|
Project Duration: 220 calendar days from Notice to Proceed |
| The following is a list of included systems: |
|
Air Handling and Ventilation Systems: (7) multi-zone units, (12) single-zone air-handling units, (6) fan coil units, (1) rooftop unit, (3) existing unit ventilators (10) exhaust fans, (7) variable frequency drives, zone control |
|
Building Control Systems (BAS/DDC) |
|
Hot Water System: (2) boilers and associated pumps |
|
Domestic Hot Water Heaters (new) |
|
Chilled Water System: (2) water-cooled chillers, (2) cooling towers and associated pumps |
|
Hydronic Flushing Participation |
|
Life-Safety (New): Fire alarm system, fire smoke damper and duct detector verification |
|
Electrical Systems (New); Electrical Distribution: including switchboards, motor-control centers, panelboards, starters, transformers, disconnect switches and lighting |
|
| PROJECT NAME: DORIS M. REED ELEMENTARY SCHOOL PROJECT |
| PROJECT DESCRIPTION: |
One 62,500-square-foot elementary school building consisting of classrooms, library, multi-purpose room, and administration offices.
|
|
Central Plant |
|
DDC |
| The following is a list of included systems: |
|
Mechanical:
Air Handling Units: Air handling units, fan coil units, exhaust fans, DX split-systems.
Chilled Water System: Air-cooled chiller, primary chilled water pumps, secondary chilled water pumps, VFDs and DDC controls. |
|
Life Safety:
Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers.
Duct Detector Verification: Verify smoke detectors installation and function. |
|
| [ Back to top ] |
OTHER PROJECTS
 |
 |
| PROJECT NAME: MORONGO CASINO |
| PROJECT DESCRIPTION: ELECTRICAL POWER GENERATION SYSTEM COMMISSIONING |
The project scope encompasses Multiple Gas Engine Generator Packages:
|
|
Witness the generator startups |
|
Preliminary load testing |
|
Control system verification |
|
Emission control system mapping |
| The following is a list of included systems: |
|
Multiple generators packaged systems |
|
Equipment and controls pertaining to the packaged generator’s operation |
|
| PROJECT NAME: LOADTEC LOADBANK INVESTIGATION |
| PROJECT DESCRIPTION: FORENSIC INVESTIGATION FOR THE FORT GREELY, ALASKA MILITARY BASE |
SCOPE OF WORK: DCSi will coordinate the activities associated with quality assurance as related to the environmental systems to confirm that the performance meets the design intent, the manufacturer’s requirements and the operational requirements of the system holistically. The following briefly describes an itemization of how this might be achieved.
|
| General Tasks: |
|
Witness initial opening of equipment shipped back to the Loadtec facility located in Las Vegas, Nevada |
|
Observe and report the condition of the Loadbank as received at the Loadtec facility |
|
Perform digital photography to record condition of received Loadbank |
|
Investigate root cause of damage |
|
Review the electrical one-line diagram, including over-current protective devices |
|
Review trending data recorded on equipment mounted monitor |
|
Review the design, materials, workmanship of Loadbank with emphasis on clearances of live parts/connections |
|
Investigate report of damaged and corrected Loadbank enclosure lighting wiring |
|
Review the heat/flash pattern resulting from equipment damage |
|
Conduct fault analysis related to Loadbank equipment damage |
|
Attend meetings as required |
|
Perform Loadbank damage assessment |
|
Compile and submit a final report |
|
| PROJECT NAME: NOS COMMUNICATIONS, INC. |
| PROJECT DESCRIPTION: POWER QUALITY STUDY |
SCOPE OF WORK : DCSi will systematically record phase currents, voltages and total KVA for the one specified location for a period of seven days.
|

|
Install and record a Power/Demand Analyzer to measure and record the current of each phase in RMS amperes and the total KVA during a period of seven consecutive days, at one location. The possible locations are as follows: |
| |
Transformer T-1
Transformer T-8
Transformer T-9 |
| |
The above locations were selected as these transformers serve the Smart Switch 6000s that are experiencing the problematic switching issues reported. |
|
Coordinate our activities with the client and occupant for the facilities (locations as specified). |
|
Monitor the recording equipment on a daily basis to ensure that it is recording without interruption(s). |
|
DCSi will provide an electrical data recording report with the RMS current and KVA demand versus time for each day of the recording and will include a hard copy of the measurements recorded at each interval in order to verify the loading of the existing circuits indicated above. (Compile all recorded data (as indicated above) and submit to client upon completion.) |
|
| PROJECT NAME: IVI INTERNATIONAL, INC. |
| PROJECT DESCRIPTION: |
105,000-square-foot building located at 2260 S. Rainbow Boulevard, Las Vegas, Nevada. One single-story retail building, constructed in 1989
|
|
Consisting of one single, single-story building |
|
No ancillary buildings or structures |
| The following is a list of included systems: |
|
Rooftop mechanical (HVAC) units |
|
Associated temperature controls (it is assumed the units are controlled via thermostats, as opposed to a DDC/BAS system) |
|
| PROJECT NAME: VEGAS LODGE NO. 32, F AND AM |
| PROJECT DESCRIPTION: |
One single-story building, constructed in 1982
|
|
Consisting of one single building with multiple closed-loop water-source heat pumps, cooling tower and boiler with associated controls. |
|
DCSi will perform an onsite evaluation of the air conditioning system and all of its components and compile a report. |
|
| PROJECT NAME: CITY OF LAS VEGAS CITY HALL EXPANSION PROJECT |
| PROJECT DESCRIPTION: DESIGN/CONSTRUCTIBILITY REVIEWS |

|
DCSi will systematically review the provided mechanical and direct digital controls (DDC/BAS) system contract documents. The review will focus on constructability of the project drawings and specifications and will include items relating to errors, omissions, and ambiguities between the contract documents. |
|