Attention to Detail is no Illusion
 
Case Projects

To date, DCSi has successfully completed approximately 500 projects. Scopes of work span design/constructibility reviews, inspection services, commissioning, retro-commissioning and recommissioning, forensic investigation, progress payment inspections, commercial building inspections, condition assessments, and power-quality studies.

We hope to illustrate the breadth of commissioning services that we offer as well as to connect you with any of our clients for a referral about our work. If you would like to talk with any of the clients listed below, contact us at (702) 942-1616 or email us at: info@LV-DCSi.com.

First LEED Project in Nevada
DCSI completes first LEED® NC project in Nevada!

LEED for New Construction and Major Renovations is a green building rating system that was designed to guide and distinguish high-performance commercial and institutional projects, with a focus on office buildings. The CCSN TELECOM BUILDING is the first building in Nevada to earn this forward-thinking LEED certification. DCSI commissioned the mechanical, life-safety and electrical systems of this project.

CCSN Telecommunications Building
PROJECT NAME: CCSN TELECOMMUNICATIONS BUILDING
PROJECT DESCRIPTION:
One 90,000-square-foot telecommunications building
Consisting of one two-story building
Central Plant
Full DDC
The following is a list of included systems:
Mechanical: Chilled water system (chiller and associated pumps), air handling and ventilation systems, DDC/BAS
Life Safety: Fire alarm – duct detectors, smoke fire dampers
Electrical: Electrical distribution, lighting, grounding/bonding
[ Back to top ]
Other LEED Projects
OTHER LEED PROJECTS CURRENTLY IN PROGRESS OR CONTRACTED
Desert Living Center

Desert Living Center
PROJECT NAME: DESERT LIVING CENTER
PROJECT DESCRIPTION:

The Desert Living Center is the “green” jewel in the crown of the Las Vegas Springs Preserve. The Desert Living Center buildings are the first platinum LEED® (Leadership in Energy and Environmental Design) buildings in the state of Nevada. These buildings embody the Preserve’s message of sustainability.

The Desert Living Center is made up of five buildings and the surrounding gardens.

Unique Aspects of this Project:

Rammed-earth walls utilizing local materials
Window design maximizing natural daylight use
Recycled materials minimizing new resource demand
Passive cooling and renewable heating of buildings
Reclaimed water to reduce tap-water needs
Electrical energy created by solar panels
The following is a list of included systems:
LEED Fundamental Commissioning of:

Mechanical

DDC Controls

Electrical Distribution

Lighting/Lighting Controls

Fire Life-Safety Equipment and Systems

 

DCSI Commissions First LEED® NC Platinum-Level Project in Nevada

DCSI has commissioned the first LEED NC Platinum-level project in Nevada: The Desert Living Center at the Las Vegas Springs Preserve. The designation, the highest a building can receive from the U.S. Green Building Council, requires that a majority of required building materials be recycled, re-used or recyclable, among other things.

Las Vegas Springs Preserve
PROJECT NAME: LAS VEGAS SPRINGS PRESERVE
PROJECT DESCRIPTION:

The $250 million Las Vegas Springs Preserve aims to be Nevada's first LEED Platinum project. It will provide space for the Nevada State Museum, Visitor's Center and the Desert Living Center interspersed among restored wetlands. It will include more than 176,000 square feet of museums, educational galleries and interactive exhibits. It will eventually include the 79,000-square-foot Nevada State Museum that is expected to open in 2009.

Unique Aspects of this Project:

It will be the first attraction in the U.S. to achieve LEED (Leadership in Energy and Environmental Design) Platinum Certification.

It is the largest commercial straw-bale project in the U.S.

Solar panels on site will generate enough solar energy to power approximately 70 percent of the Preserve attraction.

The Preserve is home to more than 250 species of wildlife.

Water on site will be filtered and reused to irrigate plants and flush toilets at the Preserve.

The following is a list of included systems:

Mechanical

DDC Controls

Electrical Distribution

Lighting/Lighting Controls

Fire Life-Safety Equipment and Systems

 
PROJECT NAME: DEPARTMENT OF EMPLOYMENT TRAINING AND REHABILITATION
PROJECT DESCRIPTION:

One 64,000-square-foot, two-story office building with public and private program spaces including a call center, training rooms, warehouse facilities and administrative offices.

The systems consist of:

Central Plant

Full DDC

Monitoring and Daylighting Controls

HVAC Underfloor Air System

Fire Alarm/Fire Detection

Chilled Water/Heating Water

Plumbing

Data, Power and Communications Distribution

This project is pursuing Silver Certification through the U.S. Green Building Council’s LEED Green Building Rating System.

Brief summary of included systems:

Mechanical:
Air Handling Units and VAVs with Reheat Coils: All air moving equipment and associated controls.
Hot-Water System: Hot-water system and all associated equipment and controls.
Chilled Water System: Chilled water system and all associated equipment and controls.

Life Safety:
Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers.
Duct Detector Verification: Verify smoke detectors installation and function.

Electrical:
Electrical Distribution System: Commissioning includes: switchboards, motor control centers, panelboards, enclosed starters, variable frequency drives, transformers, enclosed transfer switch, packaged generator, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets).
Lighting: Verify luminaire function (and associated controls), for both interior and exterior fixtures.
Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion.

 
PROJECT NAME: NEVADA POWER SOUTH OPERATIONS PROJECT #1
PROJECT DESCRIPTION:

The scope consists of three buildings.

One Office Building – 35,993 square feet
One Shop Building – 60,434 square feet
One System Control Building – 27,000 square feet

(Optional) Central Plant

Full DDC

Brief summary of included systems:

Mechanical:
Air Handling Units and VAVs with reheat coils: Air handling units, variable frequency drives for air handling units, RTUs, exhaust fans, DX split-systems.
Hot-Water System: Boilers, pumps, VFDs and associated controls
Chilled Water System: Water-cooled chillers, chilled water pumps, cooling tower pumps, cooling tower, VFDs, solids separator, and DDC controls.

Life Safety:
Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers.
Duct Detector Verification: Verify smoke detectors installation and function.

Electrical:
Electrical Distribution System: Commissioning includes: switchboards, motor control centers, panelboards, enclosed starters, variable frequency drives, transformers, enclosed transfer switch, packaged generator, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets).
Emergency Generator: Commissioning includes confirming settings match contract documents, witness loadbank testing and startup, verify shunt-trip and emergency load energization.
Lighting: Verify luminaire function (and associated controls), for both interior and exterior fixtures.
Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion.

 
PROJECT NAME: NEVADA POWER SOUTH OPERATIONS PROJECT #2
PROJECT DESCRIPTION:
The scope consists of two buildings.
One Fleet Building – 18,996 square feet
One Warehouse Building – 35,883 square feet
Total project square footage - 54,879 square feet
Brief summary of included systems:

Mechanical:
Air Handling Units and VAVs : Including air handling units, variable frequency drives for air handling units, RTUs, exhaust fans, DX split-systems.
Hot-Water System: Including boilers, pumps, electric re-heat coils in terminal boxes where heat is required, VFDs and associated controls
Chilled Water System: Including DX RTU, water-cooled chillers, chilled water pumps, cooling tower pumps, cooling tower, VFDs, solids separator, and DDC controls.

Life Safety:
Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers.
Duct Detector Verification: Verify smoke detectors installation and function.

Electrical:
Electrical Distribution System: Commissioning includes, switchboards, motor control centers, panelboards, enclosed starters, variable frequency drives, transformers, enclosed transfer switch, packaged generator, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets)
Lighting: Verify luminaire function (and associated controls), for both interior and exterior fixtures.
Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion.

[ Back to top ]
Building Commissioning
BUILDING COMMISSIONING (NEW CONSTRUCTION)
Centeniial Hills Community Center
PROJECT NAME: CENTENNIAL HILLS COMMUNITY CENTER
PROJECT DESCRIPTION:

A 98,000-square foot community center, located on 18 acres in Centennial Hills Park, features indoor and outdoor swimming pools, two gymnasiums, a dance room, fitness center, an active adult wing and space for a variety of multi-generational activities.

The following is a list of included systems:

Mechanical

DDC Controls

Electrical Distribution

Lighting/Lighting Controls

Fire Life-Safety Equipment and Systems

 
Del Sol High School
PROJECT NAME: DEL SOL HIGH SCOOL
PROJECT DESCRIPTION:

One approximately 271,040-square-foot (interior) educational building complex

Consisting of six buildings, three of which are two-story structures

Central Plant

Full Direct Digital Controls

Electrical Distribution and Lighting

MATV and Clock/Intercom

Life-Safety

The following is a list of included systems:

Air Handling and Ventilation Systems (multi-zones, fan coil units, heat pump, paint spray booth fan, fume hoods, MUAs, sawdust collector, relief fans and exhaust fans)

Hot Water System (three boilers and water heaters)

Chilled Water System (two chillers and associated pumps, two cooling towers, one heat exchanger)

Hydronic Flushing Participation

Power Distribution System

Emergency Power System

Lighting (interior/exterior)

Clock/Intercom System

MATV System

Life-Safety Systems

Brief summary of included systems:

Power Distribution System: Including switchboards, panelboards, motor control centers, transformers, enclosed starters, shunt-trip operation, surge protection devices, control devices, disconnect switches, GFI receptacles, fuses and overload heaters are installed in accordance with the contract documents.

Thermal Imaging: Thermal imaging analysis of all feeder terminations including panels, switchboards, motor control centers, transformers, chillers and air-handlers.

Grounding: Including review of electrical system grounding test reports.

Emergency Power System: Including generator and automatic transfer switch

General Lighting and Exterior Lighting Systems: Including interior, exterior and emergency lighting and associated controls.

MATV Systems: Including labeling of outlets, antenna grounding, coordination with CCSD MATV representative.

Clock/Intercom System: Including head-end equipment rack, office call-in display, clock/intercom locations, individual call-in functions, all call-function.

Life-Safety Systems: Including fire alarm system, duct detectors, fire smoke dampers

 
Cadwallader Middle School
PROJECT NAME: CADWALLADER MIDDLE SCHOOL
PROJECT DESCRIPTION:

One approximately 126,000-square-foot educational building complex

Consisting of six buildings, all of which are single-story structures

Central Plant

Full DDC

The following is a list of included systems:

Air Handling and Ventilation Systems (multi-zones, fan coil units, heat pump and exhaust fans)

Hot Water System (boilers and water heater)

Chilled Water System (chiller and associated pumps)

Hydronic Flushing Participation

Duct Detector Certification

Fire Smoke Damper Testing

Low-Voltage:
 
  • Data, CTV/MATV, Clock/Intercom, Fire Alarm System
  • Electrical Distribution:
  • Lighting, Grounding, Distribution Equipment, Generator
  •  
    PROJECT NAME: VIRGIN VALLEY ELEMENTARY SCHOOL
    PROJECT DESCRIPTION:

    One approximately 67,000-square-foot educational building complex

    Consisting of one contiguous building, all of which are single-story structures

    Central Plant

    Full DDC

    Brief summary of included systems:

    Air Handling and Ventilation Systems: (6) triple-deck multi-zones with (76) zones, (4) fan coil units, (9) exhaust fans, (6) variable frequency drives for multi-zones, (1) VFD for cooling tower, (1) unit heater (UH-1), (2) split-systems (DX-1, 2), (1) heat pump.

    Hot-Water System: (1) boiler, (2) pumps and associated controls

    Chilled Water System: (1) water-cooled chiller, (2) chiller pumps, (2) cooling tower pumps, (1) cooling tower, (1) heat exchanger and DDC controls.

    Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers.

    Duct Detector Verification: Verify smoke detectors installation and function.

    Electrical Distribution System: Commissioning includes: switchboards, motor control centers, panelboards, enclosed starters, variable frequency drives, transformers, enclosed transfer switch, packaged generator, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets).

    Lighting: Verify luminaire function and associated controls, for both interior and exterior.

    Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion.

    Data Systems: Witness contractor ping tests of: OFE data switches, IDF locations, LAN and 555 data outlets. Verify labeling of cable and data ports.

    Clock/Intercom: Witness contractor operation of office call-in display, individual call-in locations, all-call function and clock locations.

    Stand Alone Intrusion Detection System: Witness contractor operation of intrusion detection devices and keypads, per specification 16726.

    MATV: Witness contractor testing to verify validity of test report results, per specification 16750, 3.4 and 3.5.

    CCTV Surveillance System: Witness contractor testing and recording of test results, per specification 16761, 3.2.

    Public Address System: Witness contractor testing and recording of test results, per specification 16770, 3.5.

     
    PROJECT NAME: CONNERS ELEMENTARY SCHOOL
    PROJECT DESCRIPTION:

    One approximately 67,000-square-foot educational building complex

    Consisting of one contiguous building, all of which are single-story structures

    Central Plant

    Full DDC

    Brief summary of included systems:

    Mechanical:
    Air Handling and Ventilation Systems: (6) triple-deck multi-zones with (76) zones, (4) fan coil units, (8) exhaust fans, (6) variable frequency drives for multi-zones, (1) VFD for cooling tower, (1) unit heater, (1) split-system, (2) rooftop units, (1) supply fan.
    Hot-Water System: (1) boiler, (2) pumps and associated controls
    Chilled Water System: (1) water-cooled chiller, (2) chiller pumps, (2) cooling tower pumps, (1) cooling tower, and DDC controls.

    Life Safety:
    Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers.
    Duct Detector Verification: Verify smoke detectors installation and function.
    Fire Alarm System: Verify device installation and system function.

    Electrical:
    Electrical Distribution System: Commissioning includes: switchboards, motor control centers, panelboards, enclosed starters, variable frequency drives, transformers, enclosed transfer switch, packaged generator, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets).
    Lighting: Verify luminaire function (and associated controls), for both interior and exterior.
    Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion.

     
    PROJECT NAME: TANAKA ELEMENTARY SCHOOL
    PROJECT DESCRIPTION:

    One approximately 67,000-square-foot educational building complex

    Consisting of one contiguous building, all of which are single-story structures

    Central Plant

    Full DDC

    Brief summary of included systems:

    Mechanical:
    Air Handling and Ventilation Systems: (6) triple-deck multi-zones with (76) zones, (4) fan coil units, (8) exhaust fans, (6) variable frequency drives for multi-zones, (1) VFD for cooling tower, (1) unit heater, (1) split-system, (2) rooftop units, (1) supply fan.
    Hot-Water System: (1) boiler, (2) pumps and associated controls
    Chilled Water System: (1) water-cooled chiller, (2) chiller pumps, (2) cooling tower pumps, (1) cooling tower, and DDC controls.

    Life Safety:
    Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers.
    Duct Detector Verification: Verify smoke detectors installation and function.
    Fire Alarm System: Verify device installation and system function.

    Electrical:
    Electrical Distribution System: Commissioning includes: switchboards, motor control centers, panelboards, enclosed starters, variable frequency drives, transformers, enclosed transfer switch, packaged generator, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets).
    Lighting: Verify luminaire function (and associated controls), for both interior and exterior.
    Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion.

    [ Back to top ]
    Remodels / Retro-Commissioning
    REMODELS / RETRO-COMMISSIONING
    Valley High School Theater Addition
    PROJECT NAME: VALLEY HIGH SCHOOL THEATER ADDITION
    PROJECT DESCRIPTION:

    The work consists of a new Theater Building, which includes general construction and site work. The building is approximately 14,900 square feet and includes masonry, stud and stucco exterior walls, steel structural frame, built-up roof on rigid insulation on metal deck on open web steel joists with steel beams and a concrete slab-on-grade foundation. The theater has a stage that includes a fly loft with a counterweighted rigging system, stage sound and lighting systems and fixed seating.

    Brief summary of included systems:

    Ductless split-system air-conditioning unit: (4) total: (2) 1-ton and (2) 2.5-ton unit

    Packaged Rooftop Units: (1) 40-ton, (2) 12.5-ton, and (2) 8.5-ton gas-pack units

    Exhaust Fans: (4) belt-driven

    Controls associated with the above-mentioned equipment.

    Electrical Distribution System: Commissioning includes: switchboards, panelboards, enclosed starters, transformers, shunt-trip operation, disconnect switches and electrical outlets (including GFCI outlets).
    (Refer to Specification 16410, 3.4A. for enclosed starters.)
    (Refer to Specification 16426 – DCSi will verify contractor compliance with NETA ATS in accordance with Section 1.3D.)
    (Refer to Specification 16442, 3.2 and 3.3 – DCSi will verify contractor compliance.)
    (Refer to Specification 16461 – DCSi will verify noise measurement, grounding and contractor compliance with  Section 3.5A.)
     (Refer to Specification  16151 – DCSi will verify function of wiring devices.)

    Lighting: Verify luminaire function measure lighting levels, (as related to Specification 16510).
    (Refer to Specification 16510 – Adjustment and cleaning to be by the Division 16 Contractor.)

    Grounding/Bonding: Inspect main grounding connection, bonding at the service, isolated grounding system. Witness grounding test measurement. Review grounding test results for completion. (Refer to Specification 16050 and 16170.)

     
    PROJECT NAME: BRIDGER MIDDLE SCHOOL PROJECT
    PROJECT DESCRIPTION:

    One approximately 106,924-square-foot educational building complex

    Consisting of twelve buildings, all of which are single-story structures

    Central Plant – two-pipe system

    Full DDC

    Project Duration: 220 calendar days from Notice to Proceed

    The following is a list of included systems:
    Air Handling and Ventilation Systems: (7) multi-zone units, (12) single-zone air-handling units, (6) fan coil units, (1) rooftop unit, (3) existing unit ventilators (10) exhaust fans, (7) variable frequency drives, zone control
    Building Control Systems (BAS/DDC)
    Hot Water System: (2) boilers and associated pumps
    Domestic Hot Water Heaters (new)
    Chilled Water System: (2) water-cooled chillers, (2) cooling towers and associated pumps
    Hydronic Flushing Participation
    Life-Safety (New): Fire alarm system, fire smoke damper and duct detector verification

    Electrical Systems (New); Electrical Distribution: including switchboards, motor-control centers, panelboards, starters, transformers, disconnect switches and lighting

     
    PROJECT NAME: DORIS M. REED ELEMENTARY SCHOOL PROJECT
    PROJECT DESCRIPTION:

    One 62,500-square-foot elementary school building consisting of classrooms, library, multi-purpose room, and administration offices.

    Central Plant
    DDC
    The following is a list of included systems:

    Mechanical:
    Air Handling Units: Air handling units, fan coil units, exhaust fans,  DX split-systems.
    Chilled Water System: Air-cooled chiller, primary chilled water pumps, secondary chilled water pumps, VFDs and DDC controls.

    Life Safety:
    Fire/Smoke Damper Verification: Verify correct operation of fire/smoke dampers.
    Duct Detector Verification: Verify smoke detectors installation and function.

    [ Back to top ]
    Other Projects
    OTHER PROJECTS
    Morongo Casino
    PROJECT NAME: MORONGO CASINO
    PROJECT DESCRIPTION: ELECTRICAL POWER GENERATION SYSTEM COMMISSIONING

    The project scope encompasses Multiple Gas Engine Generator Packages:

    Witness the generator startups

    Preliminary load testing

    Control system verification
    Emission control system mapping
    The following is a list of included systems:

    Multiple generators packaged systems

    Equipment and controls pertaining to the packaged generator’s operation

     
    PROJECT NAME: LOADTEC LOADBANK INVESTIGATION
    PROJECT DESCRIPTION: FORENSIC INVESTIGATION FOR THE FORT GREELY, ALASKA MILITARY BASE

    SCOPE OF WORK: DCSi will coordinate the activities associated with quality assurance as related to the environmental systems to confirm that the performance meets the design intent, the manufacturer’s requirements and the operational requirements of the system holistically. The following briefly describes an itemization of how this might be achieved.

    General Tasks:

    Witness initial opening of equipment shipped back to the Loadtec facility located in Las Vegas, Nevada

    Observe and report the condition of the Loadbank as received at the Loadtec facility

    Perform digital photography to record condition of received Loadbank

    Investigate root cause of damage

    Review the electrical one-line diagram, including over-current protective devices

    Review trending data recorded on equipment mounted monitor

    Review the design, materials, workmanship of Loadbank with emphasis on clearances of live parts/connections

    Investigate report of damaged and corrected Loadbank enclosure lighting wiring

    Review the heat/flash pattern resulting from equipment damage

    Conduct fault analysis related to Loadbank equipment damage

    Attend meetings as required

    Perform Loadbank damage assessment

    Compile and submit a final report

     
    PROJECT NAME: NOS COMMUNICATIONS, INC.
    PROJECT DESCRIPTION: POWER QUALITY STUDY

    SCOPE OF WORK : DCSi will systematically record phase currents, voltages and total KVA for the one specified location for a period of seven days.

    Install and record a Power/Demand Analyzer to measure and record the current of each phase in RMS amperes and the total KVA during a period of seven consecutive days, at one location. The possible locations are as follows:

     
  • Transformer T-1
  • Transformer T-8
  • Transformer T-9
  •  

    The above locations were selected as these transformers serve the Smart Switch 6000s that are experiencing the problematic switching issues reported.

    Coordinate our activities with the client and occupant for the facilities (locations as specified).

    Monitor the recording equipment on a daily basis to ensure that it is recording without interruption(s).

    DCSi will provide an electrical data recording report with the RMS current and KVA demand versus time for each day of the recording and will include a hard copy of the measurements recorded at each interval in order to verify the loading of the existing circuits indicated above. (Compile all recorded data (as indicated above) and submit to client upon completion.)

     
    PROJECT NAME: IVI INTERNATIONAL, INC.
    PROJECT DESCRIPTION:

    105,000-square-foot building located at 2260 S. Rainbow Boulevard, Las Vegas, Nevada. One single-story retail building, constructed in 1989

    Consisting of one single, single-story building

    No ancillary buildings or structures

    The following is a list of included systems:

    Rooftop mechanical (HVAC) units

    Associated temperature controls (it is assumed the units are controlled via thermostats, as opposed to a DDC/BAS system)

     
    PROJECT NAME: VEGAS LODGE NO. 32, F AND AM
    PROJECT DESCRIPTION:

    One single-story building, constructed in 1982

    Consisting of one single building with multiple closed-loop water-source heat pumps, cooling tower and boiler with associated controls.
    DCSi will perform an onsite evaluation of the air conditioning system and all of its components and compile a report.
     
    PROJECT NAME: CITY OF LAS VEGAS CITY HALL EXPANSION PROJECT
    PROJECT DESCRIPTION: DESIGN/CONSTRUCTIBILITY REVIEWS


    DCSi will systematically review the provided mechanical and direct digital controls (DDC/BAS) system contract documents. The review will focus on constructability of the project drawings and specifications and will include items relating to errors, omissions, and ambiguities between the contract documents.